Customer

Object

Project

Realization period

ArсelorMittal Zenica

Integrated Iron-and-Steel Works in Zenica

Development of engineering documentation on reconstruction, warming and start up of coke oven battery №6 of by-product-coke plant

1999 - 2000

Restoration of work of coke oven battery №6 of by-product-coke plant and chemical recovery shops after a long shut down:

- preparatory work;

- warming up of coke oven battery with natural gas;

- charging and start-up of coke oven battery;

- start-up of chemical recovery shop;

- adjustment of machines and mechanisms' operating regime;

- adjustment of heating mode of coke ovens;

- hot repair of refractory brickwork laying of heating walls by method of ceramic welding;

- training of the personnel.

2007 - 2008