Continuing the repair work at the EVRAZ ZSMK facility
12 February 2025 0:00
OKOS team is continuing the overhaul aimed to repair coke oven batteries at EVRAZ ZSMK COBP Plant in Novokuznetsk.
In 2024, we have completed the through-wall rebuilding of 2 heating walls at COB No.7 and the rebuilding of 16 heating walls 4 to 6 flues deep at COB No.6. Besides, a package of mechanical work was carried out replacing 15 half-buckstays and flashplates at Coke Oven Battery No.6.
The customer’s feedback was positive followed by a letter of appreciation issued to confirm that OKOS is a highly qualified and competent vendor.
The 2025 repair campaign will include rebuilding of 14 heating walls of at Coke Oven Battery No.7, as well as a large a package of mechanical installation work.